Project update # 3 : where do we stand in early May?
At the project review board meeting held on 23rd April, the following key dates were confirmed: Decommissioning of roof plant 31st March – 10th May Confirmed delivery date for chillers 30th April Confirmed delivery date for AHU 2nd June Confirmed crane date / road closure – 19th June Commission of new plant - 23rd JuneRead More »Project update # 3 : where do we stand in early May?